After having the kick-off meeting for a new site survey project with your customer, which three
factors need to be considered prior to beginning a WLAN site survey? (Select three.)


A. Will an additional trip to the facility to perform the initial walkthrough be required?
B. How much time should be allocated to survey the locations for the controllers?
C. Will any additional regulatory or safety training be required to complete the site survey?
D. Is access available to all areas of the customer facility where the WLAN is planned to be deployed?
E. Which types of controllers and switches will be required to fully conduct the site survey in all areas of the customer facility?
F. Is access available to customer employees so that initial interviews can be performed?

Answer: A, C, D



The customer has an existing 802.11b/g network with Cisco 2500 controllers. The customer
would like to migrate to an 802.11a/b/g/n WLAN.
Which network infrastructure issue might impact client performance in this proposed controllerbased solution?


A. The additional application load placed on servers by 802.11n clients.
B. A bottleneck may occur if the access switch port to the AP only supports 100 Mb/s full duplex.
C. The additional load placed on a RADIUS server by 802.1X authentication traffic on the first work day of each week.
D. The added delay WDS imposes on the client when they roam from one AP to another.

Answer: B